Ok so back years ago I took this class in highschool.. but Electric and I never seen eye to eye. So I have always strayed away from it...
from the recent events in this past week/weekend.. I've gained a ton of knowledge and been wiring all kinds of chit..
I'd spent a few days in phone calls to local electrical contractors etc around town, phoning friends and people I know.. asking questions about this wiring "code" for my area??
to go back 3+ yrs ago, I went to the city office and paid the money for a seperate meter to my garage.. it was at that time that the person(s) I purchased this meter from explained to me that before they will hook me into the pole.. they inspect the wiring to make sure it's up to code? I inquired at that time what is code? briefly the guy explained: like having your junction boxes so many feet away from the main circuit box and so many outlets running off each of these junctions etc and so on an so forth? OK.. Umm how many ft? and how many outlets can I run off this? I'm not going to answer that hire an electrician... Right ok thanks..
well I did hire an electrician to just hook in my 200 amp service to the meter box $250.00 bucks later that task is completed... now to wire my garage? well at that time I was all out of cash and KY jelly...
So fast forward to this week... as I said I'm making phone calls and one was to the city office where I'd purchased the meter.. first thing they said, well this was so many years back... you'll just have to come back in and pay the $150.00 over again to get the meter box and permit! HUH? Um lady.. I own the meter box.. it's been hanging on the outside of my garage now for the 3+ past years attached to the circuit/fuse box on the other side of that wall.. it was properly installed by TD electrical contractor at that time.. all I need is power ran to the pole to the service. Well she said your going to have to pay for a new permit then... I said Excuse Me? well your other one is surely outdated? I said is that right? well ma'am I'll be down there shortly to make this payment, please pull up the paperwork showing my other permit time limet had expired and where it states this and initial it. and I'll gladly pay for another permit.. she say's well let me take your number and I'll call upstairs and see what needs to be done here? so I give it to her.. less then 2 min later she phones me back and say's I sent a workorder out to have your service connected.. I thanked her and got off the phone...
So now in the next day or two I'll have an inspector viewing my hook-ups and have a seperate service to my garage (Finally) no more runing an extension cord from the house to the garage and no more dragging that cord to different tools trying to complete my projects...
So now back to the 101.. I couldn't locate anyone who could free up their time to come assist me with this wiring.. So my sisters husband took a class on electrical wiring and has worked it in the past.. so while he's on the phone with me.. I wire up a few circuit breakers and plugs for 220 tonight...
left everything open for the inspector to view.. and if all goes well.. I'll be back in bidness tomorrow with all new Power... Sky's the Limit!!!!!
Hog